Roofing Work at the Cumberland Recreation Centre

Posted on

The Cumberland Recreation Centre is having work done on the roof expected to begin Wednesday June 24.

The process includes:

  • Replace ridge caps (Likely 2 to 4 days)
  • Pressure wash existing roof (5 days)
  • Check each fastener, tighten/replace as needed and seal each one.
  • Paint coloured sealant over entire roof structure.

This work is scheduled approximately from 7:00 am to 4:00 or 5:00 pm depending on weather. The process is expected to take between 3 to 4 weeks in total to complete.