Road and Utility Construction Projects
Posted on
Dec 8 2020 update: Work on these construction projects will continue through December into January due to a number of factors. Thank you everyone for your patience.
The following road and underground utility projects have begun and are expected to be completed by late-November:
- Derwent Avenue from Fifth to Sixth Street; Sixth Street from Derwent to Allen Avenue, lane south of Dunsmuir at Sixth Street: road, water, storm sewer, sanitary sewer
- Maryport Avenue, from Third Street to Fourth Street: road work
- Windermere Avenue from Second Street to Cumberland School; First Street from Maryport to Ulverston; Second Street from Maryport to Windermere: components of water, storm sewer, road and sidewalk along Windermere to Cumberland School Beaufort Building
- Lane north of Dunsmuir from the Museum across First Street: Storm sewer
The total budget for the capital projects including contingency and engineering fees is $1,245,077.